浅谈某水库电站的导流设计
【摘要】某电站工程电站总装机11MW,施工导流设计结合工程总体布置采用两期导流,一期先围左岸,二期围右岸的导流方式。基础砂卵石覆盖厚达7~10m。导流设计是施工组织设计的重点和难点。采用复合型围堰和多种防渗,措施,有效控制渗流,大大节约投资。
【关键词】导流设计;分期导流;复合型围堰;某电站
♪ 【Abstract】Using a power plant engineering power plant total installed capacity of 11MW, construction diversion design combines engineering general arrangement of the two diversion, a first circumference left bank, right bank of two Wai diversion way. The underlying sand and gravel cover thick 7 ~ 10m. Diversion design is the key and difficult points of the construction design. Compound cofferdam and a variety of anti-seepage measures to effectively control the flow, significant savings in investment.
☺ 【Key words】Diversion design;Stage diversion;Compound cofferdam;A power station
1. 工程概况
2. 水文地质条件
坝址河谷较宽呈“U”型。岩性为侏罗统南圆ฆ组第三段流纹质晶屑凝灰熔岩。两岸山坡残积土夹碎石厚约2~5m。左岸风化程度较右岸深,尤其左岸河边一带风化较深。河床及漫滩阶地有卵石覆盖,厚约7~10m。
4. 导流建筑物
4.4围堰防渗形式。一期纵向围堰布置在3#闸墩右侧25m处(坝0+095.3),提高建基面高程,覆盖层较浅。纵向围堰基础开挖和渗水量较小,在纵向围堰左侧填筑子堰,防渗结构采用粘土心墙结合土工膜形式。在纵向子堰的左侧依次填筑袋装砂、土工布、土工膜、土工布和粘土,防渗效果良好。
一期上下游围堰基础防渗形式在招标阶段选用旋喷砼防渗墙。这种防渗体防渗效果较有保证,基坑渗流小,但施工时间长,且其施工期内要求防渗墙两侧不能形成较大的水位差,导致基坑排水和开挖时间滞后,影响施工工期。在施工图阶段经多方面比较论证,一期上下游横向围堰采用粘土心墙结合土工膜复合防渗。这种防渗形式具有施工时段较短,不占用截流后的关键线路工期,为主体工程施工争取较多的施工时间,但需要解决防渗体水中施工的技术问题。通过调查分析,上游的水库为季调节水库,冬季库水位较低,一般不泄流。坝址来水主要为上游水库的发电泄水。因此考虑水库短时间停机,降低坝址水位,为堰基防渗体沟槽开挖施工创造条件。防渗体沟槽采用长臂反铲挖掘机开挖,倒退法施工。长臂反铲挖掘机挖深可达6~7m,基本能将覆盖层挖除。粘土填筑采取端进法施工。由于防渗土料系在水中抛填,无法压实,无法完全达到抗渗要求,故拟在粘土之后铺设一道土工膜,粘土和土工膜共同防渗,基本解决堰基渗流问题。通过几个月的观察和量测,其渗流基本控制在30m3/h之内,达到预期效果。
二期上下游围堰在导流明渠上,基础为砼底板ฝ,主要是堰体的防渗,由于堰高较小,采用粘土斜墙加铺盖的防渗形式。上游部分围堰和纵向围堰采用浆砌石加砼心墙结构防渗。
5. 结语
该电站施工导流设计,根据实际情况,选择多种围堰结构和防渗形式,有效解决了在河卵石覆盖层中的防渗问题,节约投资约100多万元。
施工导流设计中围堰结构和防渗形式的选择是设计的重点和难点。选择的是否恰当直接影响施工工期和导流投资。在经济、可行的指导原则下,结合工程总体布置和施工条件,应对围堰的布置和防渗措施进行了详细的科学论证,选择多种围堰和防渗形式,将起到缩短施工工期、降低投资的良好效益。该电站施工导流设计在这方面起到抛砖引玉的效果。